A team of 12 workers completed a job in 8 hours. How many workers are needed to finish the same job in 6 hours?

Prepare for the Pipefitting Year One Exam with engaging flashcards and multiple choice questions. Each question is accompanied by helpful hints and detailed explanations. Be ready and confident for your exam!

Multiple Choice

A team of 12 workers completed a job in 8 hours. How many workers are needed to finish the same job in 6 hours?

Explanation:
To determine how many workers are needed to finish the job in 6 hours, we first need to calculate the total amount of work done in worker-hours. A team of 12 workers can complete the job in 8 hours, which gives us a total work time of: 12 workers × 8 hours = 96 worker-hours. Now, if we want to complete the same job in 6 hours, we can set up the equation to find out how many workers are necessary for that amount of time: Total work needed is still 96 worker-hours, and this time we have 6 hours to complete the job. To find the number of workers required, we divide the total amount of work by the number of hours: Number of workers = Total worker-hours ÷ Time in hours = 96 worker-hours ÷ 6 hours = 16 workers. This shows that 16 workers would be needed to maintain the same rate of work and complete the job in 6 hours. The calculation demonstrates how workforce size and time interact to ensure project completion within specified constraints.

To determine how many workers are needed to finish the job in 6 hours, we first need to calculate the total amount of work done in worker-hours. A team of 12 workers can complete the job in 8 hours, which gives us a total work time of:

12 workers × 8 hours = 96 worker-hours.

Now, if we want to complete the same job in 6 hours, we can set up the equation to find out how many workers are necessary for that amount of time:

Total work needed is still 96 worker-hours, and this time we have 6 hours to complete the job. To find the number of workers required, we divide the total amount of work by the number of hours:

Number of workers = Total worker-hours ÷ Time in hours = 96 worker-hours ÷ 6 hours = 16 workers.

This shows that 16 workers would be needed to maintain the same rate of work and complete the job in 6 hours. The calculation demonstrates how workforce size and time interact to ensure project completion within specified constraints.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy